Home » Completed works

PORTUGAL: Lagoaça substation completed in advance

29 July 2011 No Comment

Lagoaça substationThe Electromechanics Direction has concluded the Lagoaça substation contract two months ahead of schedule, further to the customer’s request – the Portuguese Grid: Rede Eléctrica Nacional. These works amount to 800 thousand euros and involved an additional 400 kV connection to Bemposta power station and one more 400/220 kV auto-transformer. This has been performed in just four months by the High Voltage area of the Electromechanics Direction.